Fairbairn Dam Spillway Improvement Project
Infrastructure Delivery

Hartecs were engaged as the Independent Superintendent providing contract management oversight.

Hartecs Group was engaged to serve as the Independent Superintendent under the terms of the Modified 2124 Contract, overseeing essential functions such as supervision, administration, surveillance, and coordination. We worked along side Sunwaters site team to ensure the smooth and efficient delivery of the Works in full compliance with the construction Contract requirements.
 
Fairbairn Dam lies on the Nogoa River approximately 16 km southwest of Emerald in Central Queensland. The dam is a zoned rock‐fill embankment dam with a clay core and a side channel spillway. The spillway comprises a concrete lined chute with an uncontrolled ogee crest. The embankment is 823 m in length. The spillway crest and chute were constructed between 1969 and 1972 from reinforced concrete. Transverse drains were installed to facilitate under slab drainage and to assist in relieving pore pressures. The drains were constructed from earthenware pipes that were laid in a bed of gravel. Open joints between each of the pipes ensured that any water entering the gravel material is able to escape into the pipes and then out through the pipe network onto the spillway floor.
 
The scope of this contract included
  • Replacement of the Transverse Drains
  • Anchoring of the 2:1 Slope and Chute Blocks
  • Installation of Continuous Reinforced Concrete Overlay Slab

 

LocationEmerald
Client

Sunwater

SectorState Government
Expertise
Contract Administration
Project LeadBen Harte
Project Duration
2016-2017

In Progress

Status

$16m

Project Value

Other Projects